November 4, 2016 Report
Global English [ Change Region ]

November 4, 2016 Report

 
November 04, 2016   |   ShareThis

November 4, 2016 Report

Water Recovery & Additional Monitoring Well Installation

The P-4 recovery well continues to perform as expected. We completed drilling the first of four new on-site monitoring wells. Initial sampling results from the new well do not show process water impacts.

Daily Well Testing Update

As of today, Mosaic has received 1,261 well water test requests. Environmental Consulting & Technology, Inc. (ECT) is prioritizing testing based on neighbor’s proximity to the New Wales facility. Neighbors who have requested an alternative means of testing are encouraged to receive a water test at no cost from the Florida Department of Environmental Protection (FDEP).

Testing and Bottled Water Requests as of November 4, 2016

As of 12:00 pm

Scheduled 3rd party well tests 1,261
Site visits/samples taken 1,192
Expected site visits today* 22
Requests for bottled water 776

*Plans could change based on residents’ availability or inclement weather.