February 3, 2017 Report
Global English [ Change Region ]

February 3, 2017 Report

 
February 03, 2017   |   ShareThis

Progress at New Wales

Grouting

Mosaic Fertilizer started the initial phase of grouting on Wednesday. Using holes drilled from the work pad into the upper cavity, we are injecting grout (concrete mix) to fill any voids that may be present ahead of the deeper high pressure grouting to plug the sinkhole.